HYPERSCALE CAPEX $725B QUEUE 2,060 GW $/MW NoVA $1–2.3M
Section A-A · S-100 · Rev A · 06.2026

Walk the building.

Every BDG2 acquisition is underwritten as a vertical section through a high-density datacenter — rack, cooling, power, load. The shell is inherited; the power path is manufactured.

Below: a representative section through a brownfield site running institutional-scale compute. Scroll to walk the building — from rack to cooling to power to load.

DrawingS-100 Scale1/4" = 1'-0" SectionA-A
Phase: RACK
CEILING PLENUMDROP CEILINGRAISED FLOOR · CABLE TRAYEVAPORATIVE CHILLERS · 5 × 800 TONCOLDHOTCOLDHOTCOLD6 ROWS · 240 RACKS · HIGH-DENSITY LIQUID-COOLEDSVC XFMR34.5 / 13.8 kVSWITCHGEAR480'-0" BUILDING WIDTH42'-0" CLEAR HEIGHT
Phase 01 · Floor

High-density racks. Liquid-cooled.

Direct-to-chip and immersion cooling carry racks from 40 to 130 kW — load envelopes that air cooling cannot. Liquid loops shrink the white-space footprint and let an industrial shell run institutional-scale compute.

The building shell is already there — column grid, slab loading, clear height. The expensive concrete is sunk cost.

Rack density40–130 kW
CoolingDirect-to-chip / immersion
AisleContained
StandardTier III design
Phase 02 · Roof

Closed loop. Heat recovered.

Rooftop chillers feed a closed-loop cooling system through the ceiling plenum down to in-row liquid units. Recoverable heat lifts off the loop for community reuse — and the industrial roof was sized for the HVAC load.

The roof was sized for industrial HVAC. We re-use the structural envelope, not rebuild it.

LoopClosed
PUE target≤ 1.30
Heat pathCommunity reuse
Make-up waterOn-site
Phase 03 · Power

One transformer. Compliant fast-track.

Service transformer steps high-voltage transmission down to the data hall; switchgear distributes through the hall. The inherited heavy-industrial service is a load-interconnection advantage — a compliant accelerated large-load process, not a bypass of regulatory review.

The substation, the right-of-way, and the historical service were already in place. Sellers price the parcel on industrial-land comps. We underwrite it on time-to-energization.

ServiceInherited industrial
ProcessChange-of-use
PostureCompliant fast-track
Cadence~18 mo shovel-ready
Phase 04 · Fund

Fund the provable.

Once the racks come up on top of an inherited power path, the asset is no longer industrial land — it's interconnection-cleared, design-certified megawatts. That's what hyperscale capital underwrites on top.

Fund the provable; let it unlock the visionary. The first ~18 months produce the power path. Everything downstream stacks on top of it.

Critical target~500 MW
Power regionsMISO + TVA
StandardTier III TCDD
Cadence~18 mo
Hyperscale capex / 2026
~$725B
Big-Four guidance
Q1 2026 earnings
New generation lead-time
~8 yrs
National avg. to energize
RMI, Nov 2025
Stuck in queue
~2,060 GW
US interconnection backlog
LBNL, Queued Up
Powered land · NoVA
$1.0–2.3M
Per MW, entitled parcels
CBRE, H2 2025